38% PROGRESS IN THE
PUMPING &
LIFTING STATIONS
URGENT WORKS
The Ministry of Works, Municipalities
& Urban Planning Assistant Under-Secretary for Sanitary revealed that the
Ministry has achieved 38% progress in the urgent works for
the supply of pumping and lifting stations. The project is part of the
Ministry’s plan aiming to reduce sewerage networks defects.
Works involved in the project consist of surveying 71 lifting and
pumping stations, supplying and replacing some pumps and control panels and
carrying out some improvements related to electromechanical works. Lifting
pumps for 64 stations have been purchased, and work is underway to replace 37
control panels with new ones and fix 33 other control panels. Also, stations
locations have already been examined.
The Under – secretary stated that 11 stations have been supplied and
installed; A2F in Block 325 in Al Fadhel Area, A2H in Block 303 in Abu Seera
Area, A5J in Block 339 in Umm Al Hassam, B17 in Block 233 in Dair, C5B in Block
368 in Janabiya, E2E in Block 1032 in Malkiya, E2F in Block 1032 also in
Malkiya, E8E in Block 840 in Isa Town, E11D in Block 910 in West Riffa, G8 in
Block 604 in Quraya and X01A in Block 1001 in Jasra. Tests revealed that all
stations are operating well. Currently, pumps are being installed in C4C
station located in Block 404 in Sanabis.
The BD1,297,650.000 project commenced in October last year and was
awarded to Zohal Constructions.